Schedule Of Power Interruption

WHEN WHY AFFECTED SUB STATION AFFECTED AREAS
FROM: September-22-2018 08:00:00 AM
TO: September-22-2018 05:00:00 PM
  • Pull out the malfucntion PCB breaker on Power Transformer New Korea
  • Replace the rotten pole’s at Tulaoc San Simon
  • Relocation of Pole for Road Widening
  • Trimming
  • BALITE SUB STATION
  • APALIT
  • Northville
  • SV Sampaga
  • Batasan Colgante
  • Colgante
  • Sampaloc 1 2 3 4 5
  • Sampaloc Tagulod
  • Sampaloc Highway
  • Paligui
  • Ice Plant Apalit
  • Premier Hospital

  • MACABEBE
  • Telacsan
  • Tacasan
  • Saplad David
  • Nabong Danga
  • Sn Gabriel
  • San Pedro

  • SAN SIMON
  • Tulaoc
  • New Hope 4B Construction
FROM: September-10-2018 09:00:00 AM
TO: September-10-2018 05:00:00 PM
  • Rehabilitation of primary lines & replacement of wood poles
  • Trimming
  • PAU SUB STATION
  • SOME PARTS OF SAN JUAN
  • SAN PEDRO
  • SAN NICOLAS
FROM: September-07-2018 09:00:00 AM
TO: September-07-2018 05:00:00 PM
  • Rehabilitation of primary lines & replacement of wood poles
  • Trimming
  • PAU SUB STATION
  • SOME PARTS OF SAN JUAN
  • SAN PEDRO
  • SAN NICOLAS
FROM: September-05-2018 09:00:00 AM
TO: September-05-2018 05:00:00 PM
  • Rehabilitation of primary lines & replacement of wood poles Trimming
  • PAU SUB STATION
  • SOME PARTS OF SAN JUAN SAN PEDRO SAN NICOLAS
FROM: September-03-2018 09:00:00 AM
TO: September-03-2018 05:00:00 PM
  • Rehabilitation of primary lines & replacement of wood poles
  • Trimming
  • PAU SUB STATION
  • SOME PARTS OF SAN JUAN SAN PEDRO SAN NICOLAS
FROM: August-31-2018 09:00:00 AM
TO: August-31-2018 05:00:00 PM
  • Rehabilitation of primary lines & replacement of wood poles Trimming
  • PAU SUB STATION
  • SOME PARTS OF SAN JUAN
  • SAN PEDRO
  • SAN NICOLAS
FROM: August-30-2018 09:00:00 AM
TO: August-30-2018 05:00:00 PM
  • Replacement of broken wood pole & transferring of lines
  • MACABEBE SUB STATION
  • MASANTOL
  • National Road
  • San Nicolas
  • Sto Nino Market
  • Waterlily/Millionaire
  • San Isidro
  • Talba
  • Mambang
  • Pagyaba
  • Calatio
  • Sta Lucia
  • Bebe Anac
  • Bebe Matua
  • Sua
  • Cambasi
  • Sta Cruz
  • Palimpe
  • Caingin
  • Puti
  • Sagrada 1 & 2
  • San Pedro
  • Bulacus
  • Malauli
  • Nigui
  • Balibago
  • Baco
  • Alauli
  • Bagang
  • Malicaban
  • Macanuid
  • Sapang Kawayan

  • MACABEBE
  • Batasan
  • Dalayap
  • Bulati
  • Consuelo
  • San Esteban
  • Mindanao
FROM: August-29-2018 09:00:00 AM
TO: August-29-2018 05:00:00 PM
  • Rehabilitation of primary lines & replacement of wood poles
  • Trimming
  • PAU SUB STATION
  • SOME PARTS OF SAN JUAN
  • SAN PEDRO
  • SAN NICOLAS
FROM: August-10-2018 09:00:00 AM
TO: August-10-2018 01:00:00 PM
  • Replacement of rotten poles and extension of 3phase primary line Trimming
  • MACABEBE SUB STATION
  • MASANTOL
  • Bebe Anac
  • Sua
  • Cambasi
  • Sta Cruz
  • Palimpe
  • Caingin
  • Puti
  • Sagrada 1 and 2
  • San Pedro
  • Bulacus
  • Malauli
  • Nigui
  • Balibago
  • Baco
  • Alauli Bagang
  • Malicaban
  • Macanuid
  • Sapang Kawayan

  • MACABEBE
  • Consuelo
  • San Esteban
  • Mindanao
FROM: August-10-2018 09:00:00 AM
TO: August-10-2018 10:00:00 AM
  • Replacement of rotten poles and extension of 3phase primary line
  • Trimming
  • MACABEBE SUB STATION
  • Macabebe
  • Poblascion
  • Sta Cruz
  • Sto Rosario
  • San Roque
  • San Rafael
  • San Juan
  • Mataguiti
  • Sta Lutgarda
  • Sto Nino
  • Sta Maria
  • San Jose Balas
  • Castuli Biabas
  • Bituka Manok
  • Sapang Malalam
  • Maisak
  • Sta Rita
  • San Vicente
  • San Francisco
  • Batasan Bitas
  • Candelaria Guno
  • Dalayap
  • Bulati

  • Masantol
  • National Road
  • San Nicolas
  • Sto Nino Market
  • Waterlily/Millionaire
  • San Isidro
  • Talba
  • Mambang
  • Pagyaba
  • Calatio
  • Sta Lucia