Schedule Of Power Interruption

WHEN WHY AFFECTED SUB STATION AFFECTED AREAS
FROM: December-14-2018 09:00:00 AM
TO: December-14-2018 05:00:00 PM
  • Relocation of primary poles due to road widening and construction of canals
  • Trimming
  • PAU SUB STATION
  • MINALIN
  • Sta Rita
  • Sta Rita Highway
  • San Pedro
  • Sn Nicolas
  • La Loma
  • Sto Rosario
  • Sta Catalina
  • Sn Francisco
  • Bulac
  • Dawe
  • Saplad
  • Sapa Libutad
  • Dampulan
  • Maniago
  • Bituka Manok

  • MINALIN AREA EXCEPT DOMALOIS
FROM: December-07-2018 09:00:00 AM
TO: December-07-2018 05:00:00 PM
  • Installation of additional mid-spanning pole due sagging of wires
  • Replacement of rotten wood poles
  • PAU SUB STATION
  • Sto Domingo highway to CDCP
  • Caltex. 7/11 CDCP
  • Regasco
FROM: November-24-2018 07:00:00 AM
TO: November-24-2018 06:00:00 PM
  • NGCP power interruption Mexico-Calumpit (PIMU) 69kV line opening / closing of Pau ABS at STR. 045-DS to isolate / reconnect Pau-Calumpit 69kV line segment to facilitate preventive and corrective line maintenance work
  • Energization of two (2) new sets of PCBs at PELCO III Balite Sub Station as replacement of power fuses for their 2-10MVA power transformer
  • BALITE & MACABEBE SUB STATION
  • APALIT
  • MACABEBE
  • MASANTOL
  • SAN SIMON
  • San Agustin(Tulaoc)
FROM: November-24-2018 05:30:00 PM
TO: November-24-2018 06:00:00 PM
  • NGCP power interruption Mexico-Calumpit (PIMU) 69kV line opening / closing of Pau ABS at STR. 045-DS to isolate / reconnect Pau-Calumpit 69kV line segment to facilitate preventive and corrective line maintenance work
  • Energization of two (2) new sets of PCBs at PELCO III Balite Sub Station as replacement of power fuses for their 2-10MVA power transformer
  • PAU SUB STATION
  • MINALIN
  • STO TOMAS
  • SAN SIMON
FROM: November-24-2018 07:00:00 AM
TO: November-24-2018 07:30:00 AM
  • NGCP power interruption Mexico-Calumpit (PIMU) 69kV line opening / closing of Pau ABS at STR. 045-DS to isolate / reconnect Pau-Calumpit 69kV line segment to facilitate preventive and corrective line maintenance work
  • Energization of two (2) new sets of PCBs at PELCO III Balite Sub Station as replacement of power fuses for their 2-10MVA power transformer
  • PAU SUB STATION
  • MINALIN
  • STO TOMAS
  • SAN SIMON
FROM: November-23-2018 09:00:00 AM
TO: November-23-2018 04:00:00 PM
  • Erection of poles on 69kV sub transmission line at Masantol Sub Station
  • Trimming
  • MACABEBE SUB STATION
  • MACABEBE
  • Bitas
  • Cadelaria
  • San Vicente
FROM: November-22-2018 09:00:00 AM
TO: November-22-2018 05:00:00 PM
  • Relocation of primary poles due to construction of canal @ Lourdes Minalin
  • Trimming
  • PAU SUB STATION
  • MINALIN
  • Sta Maria
  • Lourdes
  • San Isidro
FROM: November-21-2018 09:00:00 AM
TO: November-21-2018 04:00:00 PM
  • Erection of poles on 69kV sub transmission line at Masantol Sub Station
  • Trimming
  • MACABEBE SUB STATION
  • MACABEBE
  • Batasan Dike
FROM: November-16-2018 09:00:00 AM
TO: November-16-2018 05:00:00 PM
  • Relocation of three phase lines at tibag san jose san simon
  • Trimming
  • PAU SUB STATION
  • SAN SIMON
  • San Jose(Fatima)
FROM: November-16-2018 09:00:00 AM
TO: November-16-2018 04:00:00 PM
  • Erection of poles on 69 KV Sub Transmission Line at Masantol Sub Station Trimming
  • MACABEBE SUB STATION
  • MACABEBE
  • Batasan Dike