Schedule Of Power Interruption

WHEN WHY AFFECTED SUB STATION AFFECTED AREAS
FROM: December-14-2017 09:00:00 AM
TO: December-14-2017 05:00:00 PM
  • Reconductoring of 3-phase primary line of feeder 1 and feeder 2 of pau sub station
  • PAU SUB-STATION
  • STA MONICA
  • SAN ISIDRO
FROM: December-14-2017 09:00:00 AM
TO: December-14-2017 05:00:00 PM
  • Transfer of loads (from BALITE SUB-STATION to PAU SUB-STATION)
  • BALITE SUB-STATION
  • STO NINO
  • SAN JOSE
  • SAN JUAN
  • SAN PEDRO
  • SAN MIGUEL
  • STA CRUZ
  • SAN NICOLAS
FROM: December-12-2017 09:00:00 AM
TO: December-12-2017 05:00:00 PM
  • Reconductoring of 3-phase primary line of feeder 1 and feeder 2 of pau sub station
  • PAU SUB-STATION
  • STA MONICA
  • SAN ISIDRO
FROM: December-09-2017 09:00:00 AM
TO: December-09-2017 05:00:00 PM
  • Erection of additional poles and replacement of rotten crossarms
  • Trimming
  • MACABEBE SUB-STATION
  • POBLACION
  • STA CRUZ
  • STO ROSARIO
  • SAN ROQUE
  • SAN RAFAEL
  • SAN JUAN
  • MATAGUITI
  • STA LUTGARDA
  • STO NINO
  • STA MARIA
  • SAN JOSE BALAS
  • CASTULI BIABAS
  • BITUKI MANOK
  • SAPANG MALALAM
  • MAISAK
  • STA RITA
  • SAN VICENTE
  • SAN FRANCISCO
  • CALDERA GUNO
  • MINDANAO
  • DALAYAP
  • BULATI
FROM: December-08-2017 09:00:00 AM
TO: December-08-2017 05:00:00 PM
  • Reconductoring of 3 phase primary line of feeder 1 and feeder 2 of pau sub station
  • PAU SUB-STATION
  • STA MONICA
FROM: December-06-2017 09:00:00 AM
TO: December-06-2017 05:00:00 PM
  • Reconductoring of 3 phase primary line of feeder 1 and feeder 2 of pau sub station
  • PAU SUB-STATION
  • STA MONICA
FROM: December-04-2017 09:00:00 AM
TO: December-04-2017 05:00:00 PM
  • Reconductoring of 3 phase primary line of feeder 1 and feeder 2 of pau sub station
  • PAU SUB-STATION
  • STA MONICA
FROM: December-02-2017 09:00:00 AM
TO: December-02-2017 05:00:00 PM
  • Reconductoring of primary line from Sn. Francisco to Poblacion Macabebe
  • Trimming Activity
  • MACABEBE SUB-STATION
  • POBLACION
  • STA CRUZ
  • STO ROSARIO
  • SAN ROQUE
  • SAN RAFAEL
  • SAN JUAN
  • MATAGUITI
  • STA LUTGARDA
  • STO NINO
  • STA MARIA
  • SAN JOSE BALAS
  • CASTULI BIABAS
  • BITUKI MANOK
  • SAPANG MALALAM
  • MAISAK
  • STA RITA
  • SAN VICENTE
  • SAN FRANCISCO
  • CALDERA GUNO
  • MINDANAO
  • DALAYAP
  • BULATI
FROM: December-01-2017 09:00:00 AM
TO: December-01-2017 05:00:00 PM
  • Reconductoring of 3 phase primary line of feeder 1 and feeder 2 of pau sub station
  • PAU SUB-STATION
  • STA MONICA
FROM: November-29-2017 09:00:00 AM
TO: November-29-2017 05:00:00 PM
  • Reconductoring of 3 phase primary line of feeder 1 and feeder 2 of pau sub station
  • PAU SUB-STATION
  • STA MONICA